Sunday, December 17, 2017

Eight kilometres of tram line in Chemnitz costs €31m

On the same day that the Luas Green line was extended to Broombridge in Dublin a new tram line was opened in Chemnitz in Saxony in Germany. Before the unification of Germany Chemnitz was called Karl Marx Stadt.

This is not comparing like with like, neverthelss some interesting facts.

The new tram line in Chemnitz runs for eight kilometres. 

It took 18 months to construct, four stops were built on the line, 80,000 cubic metres of soil was moved, 28,000 square metres was asphalted and 360 trees were planted.

The project cost approximately €31 million.

Different stats than the Dublin job.