This is not comparing like with like, neverthelss some interesting facts.
The new tram line in Chemnitz runs for eight kilometres.
It took 18 months to construct, four stops were built on the line, 80,000 cubic metres of soil was moved, 28,000 square metres was asphalted and 360 trees were planted.
The project cost approximately €31 million.
Different stats than the Dublin job.